September 2008



General Contractor Mota Engil Polska is starting road works in the area of the building. For this the Investor received a permit from Zarząd Dróg i Utrzymania Miasta for occupation of the pavements around the building.

August 2008



Finishing works in the New hotel, service and residential complex in Wroclaw are progressing. APP- Projekt as the Investor’s Representative is urging General Contractor to increase their efforts, by making mock handovers of the residential apartments.

22.08.2008
Tender procedures concerning selection of General Contractor are in progress for Project on  Bułgarska 59/61.

 05.08.2008
Acquisition of the decision for Construction Permit for the „Residential-Retail complex with office function and with underground garage”  in Poznań in Bułgarska Street.
July- August 2008
1.    Continuation  of coordination of Works over Executive Design and coordination between branches  of the Project in Paderewskiego/ Szkolna in Poznań.
2.    Preparation and distribution of the tender materials for selection of General Contractor

August 2008 Okrąglak
1.    Acquisition of  Conservator’s decision expressing agreement for  demolition of the  external staircase together  with external stairs.
2.    Coordination of the Design works - „ Construction design ” and dealing with  formal –legal issues.

Residential complex with retail area with office function and underground garage situated in Bułgarska 59/61 nearby Świerzawska and Marcelińska Street in Poznań. The Investor’s  intention first of all is to execute buildings A and B and in the second phase of buildings C and D. The total superficies of the investment is approx. 24 749 m2, of volume equal to 340 300 m3, 418 apartments, 25 office premises and 576 parking spacer. A and B buildings have been designed as buildings with 3 common underground levels destined for parking, 3 office-retail levels and 11 residential levels.
May –August 2008
Work Coordination over preparation of the full branch Construction Design for the Kiekrz MARINA   Investment, for the Construction permit.



July 2008



Procedures of handover of  retail premises in  the commercial space on level 0 have started.

15.07.2008 Okraglak
Conclusion of the Contract  between Okrąglak Development Sp. z o.o. and APP-Projekt Sp. z o.o.  for the function of Coordinator of the Project Works along with group of Supervision Inspectors.
APP is also responsible for preparation and supervision upon demolition works and for organization and running of the tender to select General Contractor.
09.07.2008 Paderewskiego Szkolna
Acquisition of a positive decision from PINB for the protection of buildings walls.
Office –Retail Building OKRAGLAK , situated in downtown of Poznań,  at intersection  of  Mielżyńskiego Street and 27 Grudnia

APP-Projekt Firm runs as the Coordinator of Design Works the Investment resting of  Renovation of the Retail Building “OKRĄGLAK” situated in Mielżyńskiego 14 / corner of 27 Grudnia streets in Poznań.
June – July 2008
1.    Continuation of coordination of works over Construction Design for Paderewskiego/Szkolna  in Poznań.
2.    Preparation of the complete documentation for running of the limited tender to select General Contractor.
3.    Acquisition of the City Conservator’s Permit  for rebuilding and modernization of buildings  situated in  Paderewskiego and Szkolna Street in Poznań.


June 2008



The procedure of final Cash settlement with AKME – Zdzisław Wiśniewski, the Contractor of excavation works and of mains replacement, have been completed. Currently the particular mains are handed over to their administrators.

June – July 2008
1.    Continuation of coordination of works over Construction Design for Paderewskiego/Szkolna  in Poznań.
2.    Preparation of the complete documentation for running of the limited tender to select General Contractor.
3.    Acquisition of the City Conservator’s Permit  for rebuilding and modernization of buildings  situated in  Paderewskiego and Szkolna Street in Poznań.
May- June 2008
1.    Coordination of design works  over construction design executed by Pracownia Architektoniczna Ewa Stanisław Sipińscy for the „Residential-retail complex with office function and underground garage”
2.    Preparation of complete documentation for running of the limited Tender for General Contractor.
3.    17.06.2008 – Distribution of tender materials for realization of the Investment on the basis of General Contracting.


May 2008



 

31st May 2008.

Also the Conservator’s Permit has been acquired.

On 8th  May 2008 new Substitute Construction Permit has been issued. The permit came in force on                  

21.05.2008
Handover to PINB of the Construction –Executive  Design for the protection of  buildings in Paderewskiego 1 and Szkolna 2 in Poznań.

06.05.2008 Kiekrz Marina
Multi- branch Concept of the Design  of  High standard recreation-apartments complex–with full surface about 10.000 .sq.m  and about . 5.500 .Sq.m  of utilitarian  superficies with underground garage, service, restaurant, fitness and  swimming pool,  approved by the  Investor.

May –August 2008

Work Coordination over preparation of the full branch Construction Design for the Kiekrz MARINA   Investment, for the Construction permit.

May- June 2008
1.    Coordination of design works  over construction design executed by Pracownia Architektoniczna Ewa Stanisław Sipińscy for the „Residential-retail complex with office function and underground garage”
2.    Preparation of complete documentation for running of the limited Tender for General Contractor.
3.    17.06.2008 – Distribution of tender materials for realization of the Investment on the basis of General Contracting.



April 2008



The installation works run in full dimension.

17.04.2008
Preparation of tender materials and distribution of introductory queries for a will of participation in limited tender procedure concerning selection of General Contractor of complex execution of „Residential-retail complex with office function and underground garage” in Poznań in Bułgarska.

April 2008 Bułgarska 59/61
Supervision over realization of demolition works.
Announcement concerning completion of demolition on 02.04.2008.


March 2008



General Contractor Mota Engil Polska has been awarded a first prize in the contests titled „ Safe Construction Site” organized by PIP.



December 2007


18.12.2007
Acquisition of the decision of construciton permit for demolition of storage-industrial buildings of CERAFM factory situated on the area  of planned investment in Bułgarska 59/61 in Poznań.
From December 2007
APP-Projekt  deals with coordination upon design works of the Investment,  resting  on rebuilding and  modernization of 2 tenement houses  situated at  interesction of Paderewskiego  and Szkolna street in Poznań. 



 

November 2007



 

31.11.2007 Paderewskiego/ Szkolna
Polka Poland  SP. z o.o. commissions  to APP-Projekt Sp. z o.o. and APP accepts commission for the function of the Project Manager, Coordinator, Inspector and Cost Manager, during realization   “turnkey in Warsaw standard”  of    “office –retail building with all the  essential connections and mains and external works in  Paderewskiego Street in Poznań .
APP is also responsible for running the tender procedure to select General Contractor, as well as for the financial control of executed complex, as well as for the creation of Supervisions Inspectors  team.

26 November 2007 Kiekrz - Marina
Signing of a contract with BBI Development NFI SA for running by Project Manager of preparation, realization of the Investment and running of the construction of the  Investment,  by fulfilling on Investor’s behalf  and favor of the managing- coordination functions against the contractors and all the entities involved in execution of the Investment (designers, contractors and suppliers); running of investor’s supervision in realization of Investment and running of a limited tender for General Contractor.

Office- retail building in Poznań in Paderewskiego/ Szkolna  Street.
APP-Projekt  runs as the Investor’s Representative modernization of 2 antique buildings in Poznan, situated in prestigious place, on the crossroad  of Paderewskiego and Szkolna street,  close to the Old Market Place.


March 2007



01.03.2007
SJM commissions to APP, and APP obliges themselvesas the Technical Advisor  to supervise the preliminary process, that is supposed to lead to acquisition of construction permit and for the selection of General Contractor for the Residential complex with office function in Bułgarska Street in Poznań.

Recreational-apartments complex Kiekrz –MARINA with underground garage, services such as restaurant, fitness, swimming pool situated at the Kierskie Lake.
APP-Projekt runs as the Investor’s representative of BBI Development NFI SA an Investment of high standard; addressed to clients interested in unique, prestigious location, of high quality architectonic solutions, deliberate function  and high quality of execution; resting on construction of recreational-apartments complex of total superficies equal to 10 000 sq. m. and of approx. 5.500 sq. m, with underground garage, services such as restaurant, fitness, swimming pool.
It is predicted to situate the complex of a height up to 3 above ground levels. Location of the plot and its coastal character invites to connect the investment with water, in the form of marina, harbor, quay. The Investment is situated in Al. Przy Jeziorze 109 in Poznań.